Project Description
Scope of Work – Feasibility, Concept Design & Preliminary BOQ
Pickleball + EV Charging Facility (Mission Viejo, CA)
Project Overview
Location: Mission Viejo, California, USA
Site Area: ~3.5 acres (partially hillside)
Land Use: Leisure
Project Type: Pickleball courts with amenities + EV fast charging
Objective
To conduct a feasibility study and develop a concept-level site plan, including quantity estimates (BOQ), to support:
Design decision-making
Budgeting
Utility coordination (SCE Rule 29)
Future permitting and contractor bidding
Phase 1: Feasibility & Concept Planning
1. Site Planning & Layout Options
Develop 2 layout options:
Option A: ~8 courts (optimized layout)
Option B: ~10 courts (maximum capacity)
Assess usable flat area considering hillside
Optimize placement of:
Courts (~20,000 sq ft)
Amenities (~10,000 sq ft)
Parking (~40,000 sq ft)
EV charging zone
2. Grading & Drainage Assessment
Preliminary grading strategy (cut/fill concept)
Identify slope constraints and feasibility
Conceptual stormwater drainage approach
Flag major risks for hillside development
3. Access & Circulation
Evaluate feasibility of new access road from service road
Internal circulation and entry/exit feasibility
Parking layout compliance (California norms – conceptual)
4. EV Charging (DCFC) Feasibility
Planning for 5 DC Fast Chargers (DCFC)
Preliminary review of:
Utility connection constraints (SCE Rule 29)
Load and transformer space requirements
Suggest optimal charger location within site
5. Regulatory & Risk Review
Identify early-stage risks related to:
City permitting (Mission Viejo)
Fire department access
Utilities (electric, telecom, water, sewer)
Highlight zoning / land use considerations
6. Preliminary BOQ / Quantity Take-Off
Consultant shall prepare a concept-level BOQ including approximate quantities for:
Site & Civil Works
Earthwork (cut, fill, grading)
Retaining walls (if required)
Internal roads and access
Parking area pavement
Sports Infrastructure
Pickleball courts (base, surfacing)
Fencing and lighting
Drainage
Stormwater drains
Swales, catch basins
Utilities & EV Infrastructure
Utility trenching / conduits
Electrical duct banks
Transformer / switchgear space
EV charger foundations / pads
Buildings & Amenities
Restrooms
Refreshment area
Seating / viewing gallery
Others
Landscaping
Miscellaneous site development works
BOQ must include:
Approximate quantities
Basis of assumptions
Separate quantities for 8-court vs 10-court layouts
Note: BOQ is preliminary for budgeting only, not for construction pricing.
Deliverables
Concept Site Plan (PDF)
8-court and 10-court layouts
Parking, amenities, EV zones marked
Feasibility Report (8–12 pages)
Site assessment
Grading & drainage summary
Access & parking feasibility
EV charging considerations
Risk analysis
Recommendation: Go / Adjust / Optimize
Concept Grading & Drainage Diagrams
Preliminary BOQ / Quantity Take-Off (Excel or PDF)
Inputs from Client
Parcel Number: 63601408 (Mission Viejo, CA)
Existing drawings (to be shared)
Access agreement (available)
Preferred court count (if decided)
Timeline
7–10 working days from project kickoff